Construction of the 4th Unloading Line


Construction of the 4th Unloading Line

12
million tons
Increase in grain transshipment capacity
250
thousand tons
Expansion of grain storage capacity
1,000
trucks per day
Increase in cargo reception speed by road transport
7,000
DWT
Organization of cargo reception from the sea for vessels
Installation of the fourth ship-loading machine
Installation of the first ship-unloading machine
realized
KSK grain terminal development program


KSK grain terminal development program

construction of the berth 40a
and dredging up to the mark 14.4
m
dredging
up to the mark 13.5 m at the berth # 40a
220
thous. tons
expansion of capacities
for grain storage
simultaneous mooring of two Panamax vessels
600
car rental per day
increasing the speed of cargo acceptance by rail and road
7
million tons
increase in grain handling capacities
Complex construction for grain handling


Complex construction for grain handling

12 silos total capacity 116 000 tons
1 600
t/hour
increasing the speed of loading onto the ship
commissioning of a plant for receiving grain with
vehicles on
two driveways and construction of a transport gallery to berths No. 40, 41
3,5
mln. tons
increase in terminal capacity
Railway complex construction


Railway complex construction

construction of berth no. 40a and dredging up to
marks 14.4 m
direct access to the railway park to control and maintain proper
path conditions
6
wagons can be processed at a time on
3 ways
150
wagons per day railway throughput
2 400
tons/h
wagons per day railway throughput
Complex construction for transshipment of KSK vehicles


Complex construction for transshipment of KSK vehicles

500
auto
capacity of one-time storage sites
10 000
auto / r
throughput